FTBA Header
 
 

BID INFORMATION   

Budget Estimate Reports for April 25, 2007 FDOT Bid Letting


NO.Ad No.Proposal IDFPNNoteCOUNTYWORK-MIXAMOUNTDAYSDIST.

#1 T1213
Bid Items
406759 2 52 01LSPOLKRESURFACING$2,943,250.00 1251
#2 T1215
Bid Items
416591 1 52 01LS/A+B/I-D/FSGLADESRESURFACING$4,233,094.00 1351
#3 T1227
Bid Items
196022 3 52 01ETC/A+B/I-D/SS/PMANATEEADD LANES & RECONSTRUCT$28,716,753.00 7501
#4 T2206
Bid Items
213323 4 52 01PDUVALINTERCHANGE RAMP (NEW)$45,907,389.00 9002
#5 T5178
Bid Items
417166 1 52 01LSBREVARDRESURFACING$2,569,953.00 625
#6 T5187
Bid Items
417182 1 52 01ETC/FS/NMPMARIONDRAINAGE IMPROVEMENTS$13,484,334.00 3755
#7 T5192
Bid Items
419678 1 52 01LSORANGESIDEWALK$540,300.00 605

TOTAL BUDGET ESTIMATE =$98,395,073.00

ETC = (More than one project no. within the contract)
* = Jobs $150,000 or Less
** = Jobs $250,000 or Less

A+B A+B Bidding Project LS Lump Sum Bidding QC2000 QC2000 Pilot Project
LR Lane Rental Project P Partnering I-D Incentive/Disincentive
BAM Bid Averaging Method GC General Contractor LSB Liquidated Savings
M Metric MS Mandatory Start OCIP Owner Controlled Ins. Program
EA Early Award QP2 Lead Based Paint W Warranty
BB Bonus Bidding SS Special Start ASB Asbestos Abatement
UU Underground Utilities ASBS As-Built Survey PB Push Button
SO Specs Only % Electronic Plans LP Landscaping Prequalification
LSIC Lump Sum Innovative Contracting MPC Mandatory Prebid Conference # $300 Job (Plan/Spec or Proposal)



 